If A completes a particular work in 8 days and B the same work in 24 days. How many days will it take if they work together?

Respuesta :

Аноним Аноним
  • 25-02-2018
A:
1 day = 1/8 of work

B:
1 day = 1/24 of the work

Together:
 1 day = A + B = 1/8 + 1/24 = 4/24 = 1/6

1 day = 1/6 of work
1/6 x 6 of work = 1 x 6 days
work =  6 days 

Answer Link

Otras preguntas

Please help it’s due tonight and have lots more to go
Write about immigration about 1,500 words in essay
- 7/3x +y to the 2nd power (if w=1 x=6 y=3) show work
Please really really need help with this
find the estimate & difference for 4-1.29
2x-6 = 3x+1-X-7 Solve the equation.
The width of a rectangle is 2x ^2 +9x -7 and length is x^2 -9
Which of the following would provide the most effective dose of live and active bacterial cultures? A. 1 teaspoon of inulin B. 1 cup of yogurt C. 1 cup of tofu
Things decided by the caste system
9. r = (-8) = 5Hey ya'll if you guys could help me figure this out it would be extremely helpful :)​