if 8 people do a job in 40 hours. How many people need to do the job in 32 hours?

Respuesta :

breadsticksandcheese
breadsticksandcheese breadsticksandcheese
  • 23-06-2021

Answer:

6 people

Step-by-step explanation:

8/40 = x/32

multiply both sides by 32: 8(32)/40 = x

x = 256/40

= 6.4

≈ 6

Answer Link

Otras preguntas

leslie bikes 10 miles each day for 100 days. how many miles did she bike in all? write your answer in standard form and in exponential form.
CAPTCHAs prevent the use of what in creating electronic contracts?
_____ Wrote the play, doctor faustus
A nurse is teaching staff about the conduction of the heart. In which order will the nurse present the conduction cycle, starting with the first structure?
What is the square root of -1/4?
Would you use more centimeters or more meters to measure the length of a car? Explain.
How many seconds there are per second
PLEASE HELP URGENT GIVING BRAINLIEST The triangles shown are similar. Which is an appropriate similarity statement for the triangles? A) ΔABC ~ ΔDEF B) ΔA
Joel is looking at a costs for using a gym. He could pay $50 per month for unlimited use or he could pay $12 per month plus $4 per visit. How many visit would h
Either the House or Senate can a bill.