What is the first phase of the project process?


A. Monitoring


B. Pre-Planning


C. Implementation


D. Planning

Respuesta :

tif21076 tif21076
  • 06-05-2021

Answer:Pre-planning

Explanation:

Answer Link
zlskfrum zlskfrum
  • 06-05-2021

Answer:

Explanation:

Implementation and Monitoring are latter phases of a project.  Pre-planning goes before Planning so the answer is B.

Answer Link

Otras preguntas

Is the system of equations consistent, consistent and coincident, or inconsistent? y=3x+4y=3x+3 Select the correct answer from the drop-down menu.
HELPPP! What is the value of x? Enter your answer, as a decimal, in the box. Do not round your answer. x=
What river do the japanese float the lanterns down for the dead?
dogs that are closely related to the coyote. Wolves are closely related to the coyote. which sentence correctly combines the sentences into one sentence with a
Using what you know about roots, prefixes, and suffixes, the word "composition" means the quality of pulling forward characterized by joining again a state o
what is the meaning of the slogan in the beginning of the speech of the need for progress
In Chapter IV of Frankenstein, Victor describes the isolation of his workshop where he performed his experiments. Which romantic stereotype of scientists is Mar
1) How does the legislative branch check executive and judicial branch? 2) How does the executive branch check the power of the legislative branch and judicial
What is 6x-7=53? X=?
why do mountaineers carry oxygen cylinders