Planned value:

How is it calculated?

Respuesta :

ZaWarud0
ZaWarud0 ZaWarud0
  • 21-10-2020
Take the planned percentage of the completed work and multiply it by the project budget and you will get Planned Value.
Answer Link

Otras preguntas

How did the Paleolithic Era and the Neolithic Era begin? Please help me
The circumference of great circle of a hemisphere is 44 cm. find the total surface area of the hemisphere​
DIG DEEPER If items plugged into a circuit use more than 2400 watts of electricity, the circuit overloads. A portable heater that uses 1050 watts of electricit
Use the distributive property to remove the parentheses. (8x-10)1/2=
The equation of a graph is 4x - 3y = 5. What is the x-intercept? A) 2 3 B) 3 4 C) 5 4 D) 5 8
For the question below, write an explanation of the short-run effect (including the determinant of AD or AS that is causing the shift, the line that shifts (AD
Explain how the processes that occur at mid-ocean ridges and ocean trenches illustrate the cycling of matter.
A team is selling pop corn for a fundraiser. The first week, they sell 500 bags. The second week, they sell 50% more than the first week. During the third week,
Amazon was valued at 430 billion dollars. Write this number in scientific notation
Four-fifths of a number exceeds two-thirds of the number by 10 what is the number