The critical path of a network is the A. path with the fewest activities. B. path with the most activities. C. shortest time path through the network. D. longest time path through the network.

Respuesta :

uzamamanzoor1271996 uzamamanzoor1271996
  • 24-02-2020

Answer:

D is correct option

Explanation:

D. longest time path through the network.

The sequence of activities within the network with zero total float is called critical path.

Answer Link

Otras preguntas

the british take over of egypt was an example of?
Why is congress barred from including conditions concerning a states government?
what is 658.129 in expanded form
write a 3-digit number using digits 2,9,4
What is the focus of Article I of the Constitution?
Complete this sequence 4.15, 6.3, 8.45
spread of desert like conditions
1.25 in expanded form
Whose geocentric model of the solar system was accepted for 1,400 years
witch defines the term spartan in modern english