Resource leveling is a network scheduling technique that seeks to assign nearly equivalent work units to each member of the project team True False

Respuesta :

Emhicee
Emhicee Emhicee
  • 26-01-2020

Answer:

False

Explanation:

Resource leveling in project management is a technique used to ensure that over-allocation of resource or conflicts as a result of over-allocation does not occur.

Cheers

Answer Link

Otras preguntas

What is the maximum cold holding temperature allowed for a cheese tray?
16. Thirteen tenths written as a decimal is:(1) 0.013 (2) 0.13 (3) 1.3 (4) 13(5) 130​
2log4x(x^3)=5log2x(x)
Research has indicated that physical punishment is the most effective kind of punishment. Please select the best answer from the choices provided ОТ
2/3 (×-7)= -2 solve for y​
A person complaining of the symptoms of inflammation and soreness in the spine and hips, as well as a skin rash, would most likely be diagnosed with...
y + 7 = - 2/5 * (x - 10) . What is theThe point-slope of the equation of the line that passes through (- 5, - 1) and (10, - 7) is standard form of the equati
A Liquid contains 250 mg of a Sabstance per milliliter.How many grams of the sabstance will 3.5 L contain?
Why do the older players occasionally watch the juniors play? A. They want to help the juniors improve their skills. B. They want to pass their time when
3. Mitosis and meiosis are similar processes, but they have some very important differences. Explain how mitosis and meiosis are alike and how they are differen