seven people need 90 days to repair and paint a heritage building.if the job should be completed in 15 days.how many more people need to be employed.​

Respuesta :

khababnazir10
khababnazir10 khababnazir10
  • 22-11-2019

Answer:

Here is your answer mate

Step-by-step explanation:

As we know that 7 person take 90 days so 1 person takes 90×7=630 days

As work has to be finished in 15 days than 630/15=42 so

42 people can complete work in 15 days but as we have already 7 people employed so required are

42-7=35 so 35 more are needed

Answer Link

Otras preguntas

for the equation x over 3 equals 15 the student found the value of x to be 5 explain the error what is the correct answer
Write a list of steps that are needed to find the measure of ∠b
I'm officially a full time wife now! It is correct grammar?
How many centi are in 12 in
Which of the following are true for terreo? Check all that apply. 1) It is a second conjugation verb. 2) The infinitive is a long E. 3) It is first person,
Joe works on an assembly line that fills boxes with various toy trinkets. Every sixth box gets a red ball and every eighth box gets a blue whistle. How often do
How do you write 701,245 in two forms
How much will you pay for 5 pounds of shrimp if the cost is 2 pounds for $10.99?
Jimmy drove 438 miles and 5 hours how many minutes will it take to travel 72 miles if he continues at the same speed
What phrase best describes the character of the young man in the memoir "A Cub Pilot"? a. Nervous and discouraged b. Energetic yet anxious C. Ambitious yet inco