Purple Swift manufactures birdhouses in lots of 10. Each birdhouse takes 30 minutes to paint. After 10 birdhouses are​ painted, the company switches paint color which requires a one hour changeover. Assume that the company should changeover at the very beginning of the process. The company works 8 hours per​ shift, one shift per​ day, 225 days per year. Currently the company has one point booth. What is Purple​ Swift's paint capacity cushion if it builds 2 comma 000 birdhouses per​ year?