P can do a piece of work in 10 days. Q can do it in 24 days. If R also works with them then it takes only 6 days to complete the whole work. In how may days R alone can complete the whole work?
A. 25
B. 40
C. 50
D. 75

Respuesta :

Otras preguntas

Maryland was once a colony of France true or false
write 968,000 in scientific notation
What did the loyalists believe about the patriots and what they were doing during the revolution?
What were England's main motives for exploring and colonizing America?
Greata uses 3 ounces of pasta to make 3/4 of serving of pasta. How many ounces of pasta are there per serving
What is the relationship between speed and steepness
What are three main support services available to members of Congress
how would congress behave differently as a unicameral legislature
What does it mean for a product of factors to be expressed using exponents
Which religious movement played a major role in increasing support for the abolitionist movement in the antebellum period?