12 workers can do a piece of work in 30 days.find how many workers should be added to finish the work in 24 days.​

Respuesta :

Otras preguntas

what's the lowest common multiple of 8 and 4
I need help with the explanation & answer to this question: "Janet's dinner costs $7.50. If she wants to leave a 10% tip, how much extra should she leave?"
how did the jamestown settlers avoid starvation
Consider a building that used 12 × 106 Btu for heating over the period of 30 days. What average power does this correspond to? Show your calculations here:
how do we get .375 into a percent
to make 2 batches of nut bars,jayda needs to use 4 eggs.how many eggs are used in each batch of nut bars
Matthew used 1/5 of a box of flour for cooking and 3/4 of the remainder to make bread.The rest of the flour was packed equally into 5 containers. What fraction
In which of the following sentences is 'but' used as a preposition? A. I wanted to leave, but I was embarrassed to do so. B. We discovered that Candy will do an
describe a theme park ride that has a constant speed but changing velocity?
the piano measures 19/4 feet long does it fit in a 5 foot long space?